If you use MS Project now you can easily and quickly prepare time location charts for your linear project schedules. We’re excited to announce that Turbo-Chart now imports and synchronizes schedule and time location data from MS Project
Try Turbo-Chart right now!
Download Turbo-Chart now with your MS Project schedule, Primavera P6 , Safran Project or any spreadsheet capable data tool.
To use this feature, follow these simple steps:
- In MS Project, add the following columns for additional data, and save your file
- Two Number Fields to enter the Location Start and Location End values
- A Text Field to enter ShapeCodes, these will be used to define how each task appears on the Time Location chart.
- Launch Turbo-Chart, Select, File > Microsoft Project > Add Microsoft Project and locate yours MS Project file
- 3) Map the import to the additional fields created above

- Press OK and your schedule data is imported. Press Ctrl+F5 to view the full range of locations and dates imported.
- Click on the ShapeCode values in Shape Library pane to customize your Shape Library
- Modify chart options by selecting Chart > Chart Options
- As you make changes in MS Project, Save the file and In Turbo-Chart Press CNTRL+R (or File > Re-Sync from source) to view the schedule changes.
- Additional projects, or comparisons can be made by importing data into new datasets (Data> Data Sets)
Further Help
Should you need further help regarding Turbo-Chart, we are here to support you!
Just send an email to support@pmerasupport.com